If you live near the Indiana Toll Road in Granger, a 30-foot sound wall is coming to the Microsoft data center site. The St. Joseph County Board of Zoning Appeals approved the proposal 4-2 Thursday, and WNDU also reported the approval. The wall would run along the north end of the site.
4-2vote to approve the sound wall
A motion to table the proposal so the board could review more studies failed before the vote.
Source: WSBT
Microsoft's Angela Smith said the company believes it meets county noise ordinances without the wall and called it a "good neighbor effort." Residents asked how the wall could affect sound from the data center and the toll road. County Council-elect Jan Cerevelli called it "a disappointing vote."
Microsoft's representative said the wall is expected to cut noise by an average of 8 to 12 decibels. When the proposal surfaced Tuesday, the estimate was 13.5 to 16.5.
The wall would be 30 feet tall, with two noise estimates on record
- 30 feet
- tall, along the north end of the site
- 8 to 12
- decibels average noise cut, per Microsoft's representative
- 13.5 to 16.5
- decibels in the estimate when the wall was proposed
- Location: along the Toll Road between Currant Road and Bittersweet Road
- Visibility: seen from the toll road, not from nearby neighborhoods
- Required: a zoning variance
- Timeline: the data center is still years from completion